Stadium and Warehouse Freezer: The work for both projects has continued with completion scheduled for this summer. Early Childhood Center: The site has been leveled and they are preparing to pour the foundation. Walking Trails and FPUE Playground: The bid was approved at the February board meeting. The work on the existing walking trails at Buckner, Blue Hills and the hard play area at the Fire Prairie playground will begin this spring. Roof Tops: The bid for roof repairs at Fire Prairie, Blue Hills and the District Warehouse were approved at the February meeting. Work will be done this summer. High School Breezeway: The bid was approved at the February meeting. Work will be done this summer and is scheduled to be completed before school begins next year. Comments are closed.
|